How do you tie the last segment to the first post to create a closed line-of-fence?


Date:
April 18, 2008
Subject:
How do you tie the last segment to the first post to create a closed line-of-fence?
Question:
How do you tie the last segment to the first post to create a closed line-of-fence?
Answer:

Due to the flexibility of the application’s building logic, there are three ways of configuring your fence. Below are screen shots of the different ways to build it and the reason why it was built that way:

Config 1:



Note that segment 8 starts from the first post in segment 1 then heads toward segment 7, closing the rectangle with the post which is segment 8.

Config 2:


You start with an existing post. The post in the end segment would be used on the first segment. You just need to choose the same diameter as your terminal post.


Config 3:



This configuration builds the segments in a counter-clockwise manner all throughout without jumping from one segment’s end to the other.